Transport infrastructure projects
ANAS S.p.A. | Autostrade per l'Italia S.p.A. | Rest of World | Public Institutions/Councils
ANAS S.p.A. |
Value (€/mln) |
Progress |
Caianello-Benevento, DG PF 07-07 motorway access road. |
480 | Initial stages |
S.S. 268 del Vesuvio, motorway lane doubling works 2nd portion, 1st e 2nd Section. |
92 | 11% |
S.S. 145 Sorrentina, construction works on the alternative route between km 11+600 and km 14+000. |
66 | 70% |
S.S. 182 Trasversale delle Serre, section IV and IV Bis. |
164 | 82% |
SS 652 Completion works, on the Fondovalle Sangro roadway section. |
26,6 | 90% |
S.S. 429 in the Val d'Elsa, construction works on the alternative route at Certaldo. |
71 | 91% |
SS 125, Barisardo. |
10,5 | Completed |
S.S. N. 45 in the Trebbia Valley modernization works on the section between the areas of Trebbia and Rio Cernusca 1st portion 1st section. |
19 | Completed |
SS 659 in the Antigorio and Formazza Valleys, construction of an alternative route between Km. 27+400 and Km. 29+750 to eliminate a series of bends in the area of "Le Casse". |
21,1 | Completed |
S.S. n. 439 Sarzanese - Valdera, implementation of adjustments and improvements of the section between Palazzo Lenzi and Bivio Rondelli. |
2,9 | Completed |
Pontedassio-Miglioramento della S.S. 28, alternative route between km 132+700 and il km 136+700- Section n. 1 between km 132,700 and 134,800. |
24,9 | Completed |
S.S. 453, implementation of the alternative route between km. 4+300 and 6+600 in the urban area of Borghetto D'Arroscia. |
13,3 | Completed |
Completion works on the alternative route of ITTIRI from km 26+700 to SP n. 18 Usini-Ittiri -Romana of the SS 131 bis "Carlo Felice". |
1,9 | Completed |
P52 S. Bartolomeo, Regalseni turn-off at the S.S. 117 bis intersection. |
19,6 | Completed |
S.S. 16, alternative route to the Motorway section between Riccione and Misano Adriatico. |
21 | Completed |
S.S. 10 Padana Inferiore and S.S. 494 Vigevanese, construction of the alternative route for Alessandria - Portion 3 - 1° Section. |
53 | Completed 09/08 |
S.S Aurelia 1 and S.S. 582 in the Colle San Bernardo area, alternative route to the S.S 1 Aurelia. |
42,3 | Completed |
S.S. n° 1 Via Aurelia, construction of the alternative route to the SS 1 in the area of Vado Ligure – Portions 4 and 5 - S. Nicolò Tunnel and turn-off. |
21 | Completed 02/08 |
S.S. 106 Jonica, road surface improvements - Portion 7 at Scanzano. |
12 | Completed 05/05 |
Motorway E/78, work conversion to 4 lanes insection Siena-Betolle- Portion 2. |
24 | Completed |
S.G.C. Grosseto - Fano – Section between Grosseto and Siena , Portion 10°, work on conversion to 4 lanes. |
29 | Completed 12/11 |
SS 125 Orientale Sarda, construction of new road S.S. 125, section Tertenia - Tortolì - Portion 3° Section 3°. |
10,2 | Completed 05/09 |
SS 125 Orientale Sarda, construction of new road S.S. 125, section S. Priamo - Muravera, Portion 4° Section 2°. |
27 | Completed 06/06 |
S.S. 617 Bronese, modernization works and road surface improvements- 1° Portion. |
8 | Completed 06/08 |
S.S. 23 in the Sestriere area, construction work on the alternative route at Stupinigi. |
5,2 | Completed 11/05 |
SS 125 Orientale Sarda, construction of the new S.S. 125, section Tertenia-Tortolì-Portion 3° Section 1° and 2°. |
17,1 | Completed 01/10 |
S.S. 337 in Val Vigezzo, work on implementation of safety measures on the section between km 7+300 e 8+450 (Paiesco tunnel). |
26 | Completed 07/10 |
Panoramica Zegna, construction of the alternative route to the S.S. |
30 | Completed |
Salerno - Reggio Calabria Motorway construction, Portion 1 section 5. |
14,1 | Completed |
Salerno - Reggio Calabria Motorway, Part 3° - section 2°, Portion 4° from 383+000 to km 393+500. |
44 | Completed 10/07 |
DG 21/04, construction of the E90, section S.S. 106, from the Squillace turn-off (km 178+350) to the Simeri Crichi turn-off (km 191+500) and extension of the S.S. 280 "Dei due Mari" from the S.Sinato turn-off to the Germaneto turn-off. |
12,5 | Completed |
SS 376, construction from Km 2+300 to Km 6+00. |
9,9 | Completed |
Salerno-Reggio Calabria Motorway, ASR 86/00 - Rosarno Gioiatauro. |
37 | Completed |
AUTOSTRADE PER L'ITALIA S.p.A. |
Value (€/mln) |
Progress |
Autostrade Meridionali (Southern Motorways) A3 Napoli – Salerno, conversion to three lanes of the Torre del Greco - Torre Annunziata section. |
63 | 68% |
Motorway MI-NA, conversion to three lanes of the Firenze Nord - Firenze Sud section, portions 4,5 and 6 (Section B). |
312 | 83% |
Motorway MI-NA, widening of the third lane of the Barberino del Mugello - Incisa Valdarno segment, sections 7 e 8 ( Section C). |
187 | 89% |
Autostrade Meridionali A3 Napoli - Salerno, Pompei turn-off. |
28 | 94% |
Motorway MI-NA,improvement of the Apennine crossover section between Sasso Marconi and Barberino del Mugello, section La Quercia - Badia Nuova, Portion 5a. |
215 | 95% |
Motorway MI-NA, improvement of the Apennine crossover section between Sasso Marconi and Barberino del Mugello, Portion 12 and Barberino exit. |
187 | 99% |
Fiori Motoray, by-pass of the S.S. n. 1 Aurelia. Section: Vado Celle Ligure 1° First operational phase. Portion n. 2 Bis: completion works on portion n. 2. |
2,438 | Completed |
Motorway MI-NA,improvement of the Apennine crossover section at Sasso Marconi - La Quercia - Portion 4. |
38 | Completed 04/08 |
MI-NA Motorway Network,widening of the third lane section between Casalecchio Reno - Sasso Marconi- Portion 0. |
59 | Completed 02/10 |
Sicilian Motorway, A18 Siracusa Section 4, Gela "Noto". |
68 | Completed |
Sicilian Motorway, A18 Siracusa Section 5, Gela "Rosolini". |
52 | Completed |
Sicilian Motorway, Viaduct Pollina Portion 30. |
9,3 | Completed |
Rest of World |
Value (€/mln) |
Progress |
Oman, construction motorway junction Al Rabat-Salalah. |
43 | Underway |
Bulgaria, design and construction of the Motorway Stuma – Dolna Dkania – Dupnitca. |
30 | 5% |
Kazakhstan, Civil Works under South - West Roads Project : " West Europe - West China " International Transit Corridor (Carec ib & 6b) IBRD Loan n° 7681. |
63 | 25% |
Azerbaijan, Azer Road Service.East - West Highway Improvement Project. Ganjia Bypass Section. |
45 | 65% |
Azerbaijan, Azer Road Service East - West Highway Improvement Project. Gazack - Georgian Border Section. |
35 | Completed |
Greece, Egnatia Odos. Sellon – Ioanninon segment. |
112 | Completed |
Vietnam Overhauling of road surfacing and of 11 bridges between the cities of NA TRANG and HO CHI MINH. |
17,7 | Completed |
Albania, Motorway construction of VORE-DURRES-2° Portion SUKTH-DURRES. Section of dual-lane motorway plus emergency lane in both directions. Bridges and steel fibre reinforced concrete raised sections. |
20,8 | Completed |
Public Institutions/Councils |
Value (€/mln) |
Progress |
Ministry of Development, INFRASUD. |
214 | Initial stages |
Council of Catania,completion of dual-carriage way |
50 | Completed |
Quadrilateral Umbria Marche, DIRPA SCARL. |
716 | 11% |
Vallo di Lauro S.p.A, express fast-flowing road Vallo di Lauro. Caserta-Salerno Motorway Portion 1° e 2°. |
38 | 12% |
Province of Cosenza, SS Silana-Sibari. |
12 | 25% |
Province of Arezzo, work on the alternative route to the S.R. N° 69 from Levane to San Giovanni Valdarno (Arezzo). |
32 | 57% |
COPIN Consortium, C15. |
3,7 | 74% |
COPIN Consortium, Via Sartania. |
16,8 | 86% |
Council of Senobi Monastir. |
0,3 | Completed |
Province of Sassari, construction of the Valle dei Giunchi new road from S'SISCIA to the SP 97. |
2,05 | Completed |
Torino 2006 Agency, alternative route of the SS del Sestriere alongside the built-up area of Porte. |
49 | Completed 11/05 |