Transport infrastructure projects

Print

ANAS S.p.A. | Autostrade per l'Italia S.p.A. | Rest of World | Public Institutions/Councils

ANAS S.p.A.

Value
(€/mln)
Progress

Caianello-Benevento, DG PF 07-07 motorway access road.

480 Initial stages

S.S. 268 del Vesuvio, motorway lane doubling works 2nd portion, 1st e 2nd Section.

92 11%

S.S. 145 Sorrentina, construction works on the alternative route between km 11+600 and km 14+000.

66 70%

S.S. 182 Trasversale delle Serre, section IV and IV Bis.

164 82%

SS 652 Completion works, on the Fondovalle Sangro roadway section.

26,6 90%

S.S. 429 in the Val d'Elsa, construction works on the alternative route at Certaldo.

71 91%

SS 125, Barisardo.

10,5 Completed

S.S. N. 45 in the Trebbia Valley modernization works on the section between the areas of Trebbia and Rio Cernusca 1st portion 1st section.

19 Completed

SS 659 in the Antigorio and Formazza Valleys, construction of an alternative route between Km. 27+400 and Km. 29+750 to eliminate a series of bends in the area of "Le Casse".

21,1 Completed

S.S. n. 439 Sarzanese - Valdera, implementation of adjustments and improvements of the section between Palazzo Lenzi and Bivio Rondelli.

2,9 Completed

Pontedassio-Miglioramento della S.S. 28, alternative route between km 132+700 and il km 136+700- Section n. 1 between km 132,700 and 134,800.

24,9 Completed

S.S. 453, implementation of the alternative route between km. 4+300 and 6+600 in the urban area of Borghetto D'Arroscia.

13,3 Completed

Completion works on the alternative route of ITTIRI from km 26+700 to SP n. 18 Usini-Ittiri -Romana of the SS 131 bis "Carlo Felice".

1,9 Completed

P52 S. Bartolomeo, Regalseni turn-off at the S.S. 117 bis intersection.

19,6 Completed

S.S. 16, alternative route to the Motorway section between Riccione and Misano Adriatico.

21 Completed

S.S. 10 Padana Inferiore and S.S. 494 Vigevanese, construction of the alternative route for Alessandria - Portion 3 - 1° Section.

53 Completed 09/08

S.S Aurelia 1 and S.S. 582 in the Colle San Bernardo area, alternative route to the S.S 1 Aurelia.

42,3 Completed

S.S. n° 1 Via Aurelia, construction of the alternative route to the SS 1 in the area of Vado Ligure – Portions 4 and 5 - S. Nicolò Tunnel and turn-off.

21 Completed 02/08

S.S. 106 Jonica, road surface improvements - Portion 7 at Scanzano.

12 Completed 05/05

Motorway E/78, work conversion to 4 lanes insection Siena-Betolle- Portion 2.

24 Completed

S.G.C. Grosseto - Fano – Section between Grosseto and Siena , Portion 10°, work on conversion to 4 lanes.

29 Completed 12/11

SS 125 Orientale Sarda, construction of new road S.S. 125, section Tertenia - Tortolì - Portion 3° Section 3°.

10,2 Completed 05/09

SS 125 Orientale Sarda, construction of new road S.S. 125, section S. Priamo - Muravera, Portion 4° Section 2°.

27 Completed 06/06

S.S. 617 Bronese, modernization works and road surface improvements- 1° Portion.

8 Completed 06/08

S.S. 23 in the Sestriere area, construction work on the alternative route at Stupinigi.

5,2 Completed 11/05

SS 125 Orientale Sarda, construction of the new S.S. 125, section Tertenia-Tortolì-Portion 3° Section 1° and 2°.

17,1 Completed 01/10

S.S. 337 in Val Vigezzo, work on implementation of safety measures on the section between km 7+300 e 8+450 (Paiesco tunnel).

26 Completed 07/10

Panoramica Zegna, construction of the alternative route to the S.S.

30 Completed

Salerno - Reggio Calabria Motorway construction, Portion 1 section 5.

14,1 Completed

Salerno - Reggio Calabria Motorway, Part 3° - section 2°, Portion 4° from 383+000 to km 393+500.

44 Completed
10/07

DG 21/04, construction of the E90, section S.S. 106, from the Squillace turn-off (km 178+350) to the Simeri Crichi turn-off (km 191+500) and extension of the S.S. 280 "Dei due Mari" from the S.Sinato turn-off to the Germaneto turn-off.

12,5 Completed

SS 376, construction from Km 2+300 to Km 6+00.

9,9 Completed

Salerno-Reggio Calabria Motorway, ASR 86/00 - Rosarno Gioiatauro.

37 Completed

AUTOSTRADE PER L'ITALIA S.p.A.

Value
(€/mln)
Progress

Autostrade Meridionali (Southern Motorways) A3 Napoli – Salerno, conversion to three lanes of the Torre del Greco - Torre Annunziata section.

63 68%

Motorway MI-NA, conversion to three lanes of the Firenze Nord - Firenze Sud section, portions 4,5 and 6 (Section B).

312 83%

Motorway MI-NA, widening of the third lane of the Barberino del Mugello - Incisa Valdarno segment, sections 7 e 8 ( Section C).

187 89%

Autostrade Meridionali A3 Napoli - Salerno, Pompei turn-off.

28 94%

Motorway MI-NA,improvement of the Apennine crossover section between Sasso Marconi and Barberino del Mugello, section La Quercia - Badia Nuova, Portion 5a.

215 95%

Motorway MI-NA, improvement of the Apennine crossover section between Sasso Marconi and Barberino del Mugello, Portion 12 and Barberino exit.

187 99%

Fiori Motoray, by-pass of the S.S. n. 1 Aurelia. Section: Vado Celle Ligure 1° First operational phase. Portion n. 2 Bis: completion works on portion n. 2.

2,438 Completed

Motorway MI-NA,improvement of the Apennine crossover section at Sasso Marconi - La Quercia - Portion 4.

38 Completed
04/08

MI-NA Motorway Network,widening of the third lane section between Casalecchio Reno - Sasso Marconi- Portion 0.

59 Completed
02/10

Sicilian Motorway, A18 Siracusa Section 4, Gela "Noto".

68 Completed

Sicilian Motorway, A18 Siracusa Section 5, Gela "Rosolini".

52 Completed

Sicilian Motorway, Viaduct Pollina Portion 30.

9,3 Completed

Rest of World

Value
(€/mln)
Progress

Oman, construction motorway junction Al Rabat-Salalah.

43 Underway

Bulgaria, design and construction of the Motorway Stuma – Dolna Dkania – Dupnitca.

30 5%

Kazakhstan, Civil Works under South - West Roads Project : " West Europe - West China " International Transit Corridor (Carec ib & 6b) IBRD Loan n° 7681.

63 25%

Azerbaijan, Azer Road Service.East - West Highway Improvement Project. Ganjia Bypass Section.

45 65%

Azerbaijan, Azer Road Service East - West Highway Improvement Project. Gazack - Georgian Border Section.

35 Completed

Greece, Egnatia Odos. Sellon – Ioanninon segment.

112 Completed

Vietnam Overhauling of road surfacing and of 11 bridges between the cities of NA TRANG and HO CHI MINH.

17,7 Completed

Albania, Motorway construction of VORE-DURRES-2° Portion SUKTH-DURRES. Section of dual-lane motorway plus emergency lane in both directions. Bridges and steel fibre reinforced concrete raised sections.

20,8 Completed

Public Institutions/Councils

Value
(€/mln)
Progress

Ministry of Development, INFRASUD.

214 Initial stages

Council of Catania,completion of dual-carriage way

50 Completed

Quadrilateral Umbria Marche, DIRPA SCARL.

716 11%

Vallo di Lauro S.p.A, express fast-flowing road Vallo di Lauro. Caserta-Salerno Motorway Portion 1° e 2°.

38 12%

Province of Cosenza, SS Silana-Sibari.

12 25%

Province of Arezzo, work on the alternative route to the S.R. N° 69 from Levane to San Giovanni Valdarno (Arezzo).

32 57%

COPIN Consortium, C15.

3,7 74%

COPIN Consortium, Via Sartania.

16,8 86%

Council of Senobi Monastir.

0,3 Completed

Province of Sassari, construction of the Valle dei Giunchi new road from S'SISCIA to the SP 97.

2,05 Completed

Torino 2006 Agency, alternative route of the SS del Sestriere alongside the built-up area of Porte.

49 Completed 11/05
.